Site Update, 7/2/26

Here are some new photos of the current state of things. 

 The septic tanks have been installed, and we will be putting the drain field in soon. The electrician has started his rough in for the main panel in the addition, and once he is finished, we can come out and pour the slab. 

We will be out some time next week to replace parts of the erosion control as it is starting to show its age, and several branches have fallen on it. It's currently repaired and in working order. 

The building itself is now sealed against the weather, and we will finish putting the vapor barrier up as soon as it arrives. 

-Site Contractors

Next
Next

05/20/26 LPD Inspection